Erection of wind turbines starts in Muukko
Press Contacts
Visit our media section and follow the link "Press contacts"
The erection of the seven ECO110 wind turbines for the Muukko 21 MW wind farm will start in Lappeenranta during week 8 with the preparatory site works.
The five meter high foundations of the wind turbines are ready on site.
The big parts of the wind turbines (blades, nacelles and the tower parts) will be transported from the port of Hamina during week 9. The big components require special transportation vehicles which can disturb the normal traffic on the roads.