An ALSTOM-led consortium has just signed a contract, valued at approximately 67 million euro, with the Hebei Zhanghewan Pumped Storage Company Ltd., to supply equipment to the Zhanghewan pumped-storage hydropower station (4 x 255 MW), located in Chinas north-east Hebei Province
ALSTOMs share of the contract is around 34 million euro and scope of supply includes four pump-turbines, governing systems, control systems, spherical inlet valves, mechanical auxiliaries, and a static frequency converter. The first unit is expected to enter commercial operation in early 2007 and the last unit in 2008.
The other consortium member, Voith Fuji Hydro of Japan, will supply four motor-generators, excitation systems and other electrical auxiliaries.
Financed by loans from the Asian Development Bank, the Zhanghewan project is designed to have multiple functions. When completed, the plant will supply a load smoothing capacity of 2000 MW to the Hebei Southern Power Grid. The heightened dam will allow better flood prevention and control, increase the downstream irrigation area, and also provide drinking water to areas along both banks of the lower Gantao River.
An ALSTOM-led consortium has just signed a contract, valued
at approximately 67 million euro, with the Hebei Zhanghewan
Pumped Storage Company Ltd., to supply equipment to the
Zhanghewan pumped-storage hydropower station (4 x 255
MW), located in China’s north-east Hebei Province
ALSTOM’s share of the contract is around 34 million
euro and scope of supply includes four pump-turbines, governing
systems, control systems, spherical inlet valves, mechanical
auxiliaries, and a static frequency converter. The first unit
is expected to enter commercial operation in early 2007 and the
last unit in 2008.
The other consortium member, Voith Fuji Hydro of Japan, will
supply four motor-generators, excitation systems and other
electrical auxiliaries.
Financed by loans from the Asian Development Bank, the
Zhanghewan project is designed to have multiple functions. When
completed, the plant will supply a load smoothing capacity of
2000 MW to the Hebei Southern Power Grid. The heightened
dam will allow better flood prevention and control, increase
the downstream irrigation area, and also provide drinking water
to areas along both banks of the lower Gantao
River.
Press Enquiries :
Paola TIZIONI
Tel. : +33 (0) 134 65 42 05
Fax. : +33 (0) 134 65 47 49
paola.tizioni@chq.alstom.comProject contact :
Zhong Qiu SHAO
Tel. : + 86 10 6410 6235
Fax. :
zhongqiu.shao@power.alstom.com
Should you have any media inquiries about this press release, do not hesitate to contact our team.