ALSTOM has recently signed two separate contracts with a total value of
over 56 million euros for two hydro power projects in China.

The first contract, signed with Hunan Zhongfang Tongwan Hydro Co., Ltd.,  is for the supply of four 45MW Bulb turbine/generator units with runner diameter of 7.1 m to the Tongwan hydropower station, located on the Yuan river in China's southern Hunan province. Site work began in December 2004 and the first unit is expected to enter commercial operation at the end of 2007. 

The second, where ALSTOM is in consortium with Harbin Electric Company, is for the supply of six 780MVA generators to the Xiaowan hydro power station (6 X 700 MW), located on the Lancang River in Chinas southwestern Yunan Province. The customer is the Yunnan Huaneng Lancangjiang Hydropower Development Co., Ltd.  Commissioning of the first unit is scheduled for the beginning of 2009 and the completion of the project is expected  by 2011.

Frederic Schneider-Maunoury, managing director of ALSTOMs Hydro Power Business, said: After an extremely successful year in 2004 in China, where our order-intake was in excess of 600 million euros, we are indeed very pleased to start off 2005 with these two contracts. They demonstrate the strong position of ALSTOM in China's hydro power market and customer confidence in our technology. "

alstom.jpg

The first contract, signed with Hunan Zhongfang Tongwan Hydro Co., Ltd.,  is for the supply of four 45MW Bulb turbine/generator units with runner diameter of 7.1 m to the Tongwan hydropower station, located on the Yuan river in China's southern Hunan province. Site work began in December 2004 and the first unit is expected to enter commercial operation at the end of 2007. 

The second, where ALSTOM is in consortium with Harbin Electric Company, is for the supply of six 780MVA generators to the Xiaowan hydro power station (6 X 700 MW), located on the Lancang River in China’s southwestern Yunan Province.

The customer is the Yunnan Huaneng Lancangjiang Hydropower Development Co., Ltd.  Commissioning of the first unit is scheduled for the beginning of 2009 and the completion of the project is expected  by 2011.

Frederic Schneider-Maunoury, managing director of ALSTOM’s Hydro Power Business, said: “After an extremely successful year in 2004 in China, where our order-intake was in excess of 600 million euros, we are indeed very pleased to start off 2005 with these two contracts. They demonstrate the strong position of ALSTOM in China's hydro power market and customer confidence in our technology. "

Should you have any media inquiries about this press release, do not hesitate to contact our team.

Your press contacts